Approve Change Order #1F to Western Construction, Inc. for Street Rehab - West Blvd Inlay (Flormann to Saint Patrick), Project# 2817 / CIP #51262 for a decrease of $7,849.20.

Origination Group:
Public Works Committee
Origination Meeting Date:
10/14/2025
City Council Hearing Date:
10/20/2025
Staff Contact:
Roger Hall
Agenda Item Summary:
This is a final change order reconciling final quantities. Final project cost is $534,509.80.