Posted: May 09, 2025
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW051325-01

Agenda Item Title:

Approve Change Order 2F To PKG Contracting, Inc. For The Water Reclamation Facility Aeration Basin Clariflocculator. Project No. 2629/CIP No. 51129 For A Decrease Of $111,206.00. This Is The Final Change Order Reconciling Final Quantities.

Origination Group:
Public Works Committee
Origination Meeting Date:
05/13/2025
City Council Hearing Date:
05/19/2025
Staff Contact:
Eduardo Lopez
Agenda Item Summary:
Change Order No. 2F addresses adjustments to the Water Reclamation Facility Aeration Basin Clariflocculator project credits. Specifically, the change order includes contract adjustments reflecting cost savings identified during construction.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Enterprise Water Reclamation
Is Funding Budgeted?:
Budgeted

Recommendations: