Agenda Item Summary

Agenda Item Ref. #: PW091223-05

Agenda Item Title:

Approve Change Order 1 for Project No. 21-2670 / CIP No. 51170 Signal Drive and Kellogg Place Street and Utility Reconstruction with Simon Contractors of SD, Inc. for an increase of $8.336.76.

Origination Group:
Public Works Committee
Origination Meeting Date:
09/12/2023
City Council Hearing Date:
09/18/2023
Staff Contact:
Roger Hall
Agenda Item Summary:
Additional items needed due to existing water mains breaking during the course of construction.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Water Replace/Improve
Is Funding Budgeted?:
Budgeted

Recommendations: