Posted: June 09, 2023
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW061323-03

Agenda Item Title:

Approve Change Order #1-Final for RCPD SW Precinct Renovation - Project #2714 CIP #51368 with Lost Cabin Constructors, Inc. for an increase of $11,996.78.

Origination Group:
Public Works Committee
Origination Meeting Date:
06/13/2023
City Council Hearing Date:
06/20/2023
Staff Contact:
Rod Johnson
Location:
SW PD Precinct
Agenda Item Summary:
Renovation of former Security First Bank Building at Sheridan Lake Road and Catron Blvd. Primary increase was for changes in the plan that required two additional doors and the addition of a storage closet due to a hidden existing column and roof drains.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Gov't Buildings
Is Funding Budgeted?:
Budgeted

Recommendations: