Posted: February 25, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW030122-04

Agenda Item Title:

Approve Change Order #4 to Simon Contractors of SD Inc. for 2020 Miscellaneous Improvements Projects, General Civil Projects, Project 20-2605 / CIP 51132.1 for no cost change.

Origination Group:
Public Works Committee
Origination Meeting Date:
03/01/2022
City Council Hearing Date:
03/07/2022
Staff Contact:
Eddie Lopez
Agenda Item Summary:
Change Order #4 will add 3 new bid items that will address the repair of shorted electrical lines that were encountered during excavation activities, additional grading work that was required for the installation of erosion control measures around a drainage ditch, and the removal of a temporary construction access road. This change order also credits the project back with an installed quantity adjustment for earthwork required for pipe culvert undercut activities, bringing Change Order #4 to a net zero cost change order.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center

Recommendations: