Posted: October 22, 2021
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW102621-01

Agenda Item Title:

Approve Change Order #9F to Simon Contractors of SD, Inc. for E Blvd E North Utility Reconstruction, Project 14-2170/CIP 50866.1 for a decrease of $376.96

Origination Group:
Public Works Committee
Origination Meeting Date:
10/26/2021
City Council Hearing Date:
11/01/2021
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve Change Order #9F to Simon Contractors of SD, Inc. for E Blvd E North Utility Reconstruction, Project 14-2170/CIP 50866.1 for a decrease of $376.96. Adjustments made for actual quantities used to complete the project.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
604 833
101 301
602 933
505 8911
Is Funding Budgeted?:
Budgeted

Recommendations:

Attachments & Links to Download:

PW102621-01 Project 2170 Change Order 