Posted: September 26, 2019
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW100119-16

Agenda Item Title:

Authorize Mayor and Finance Officer to sign agreement between the City of Rapid City and Dakota Pump, Inc. (DPI) for Professional Services Supervisory Control and Data Acquisition (SCADA) improvements associated with the Water Reclamation Facility Digester MCC and UV/Admin. Transfer Switch Replacement, Project No. 19-2485/CIP No. 51216 in the amount of $6,780.00.

Origination Group:
Public Works Committee
Origination Meeting Date:
10/01/2019
City Council Hearing Date:
10/07/2019
Staff Contact:
Stacey Titus
Location:
Water Reclamation Facility
Agenda Item Summary:
The Water Reclamation Facility (WRF) needed to replace the existing Digester Facility MCC as it had exceeded its’ design life and its’ condition had deteriorated. The UV/Admin. Transfer Switch was determined to be deficient and in need of replacement too. A contract to replace these items was awarded to MAC Construction Company. As part of the project with MAC the City’s SCADA Contractor, DPI, is responsible for I/O point verification and communication for the facility’s SCADA system as well as performing the SCADA system reprograming for the newly installed components.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
604 7072
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve