Agenda Item Summary

Agenda Item Ref. #: PW061119-05

Agenda Item Title:

Authorize lowering the percentage of work that the Contractor must perform, within their own organization, from 50% to 35% for the Pavement Rehabilitation Project – Fountain Plaza Drive and Rand Road. Project Number 18-2471/ CIP # 50549.

Origination Group:
Public Works Committee
Origination Meeting Date:
06/11/2019
City Council Hearing Date:
06/17/2019
Staff Contact:
Sara Oden
Location:
Fountain Plaza Dr and Rand Rd ROW
Agenda Item Summary:
Revise Paragraph 7.40 of Section 7 – General Conditions of the City of Rapid City Standard Specifications to allow the Contractor to perform not less than 35% of the work with his own organization instead of the standard 50%.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

PW061119-05 Project 2471 Memo to PW Director