Approve Change Order 1F to Action Mechanical, Inc. for Red Rock Booster Pump Station Improvements, Project No. 14-2177 / CIP No. 50812.B for a decrease of $29,160.00.

Origination Group:
Public Works Committee
Origination Meeting Date:
06/12/2018
City Council Hearing Date:
06/18/2018
Staff Contact:
Morgan Falcone
Agenda Item Summary:
Changes included the addition of pipe supports for pumping components, the addition of drain piping for an air release valve, the addition of recirculation piping for the jockey pump, the addition of domestic water piping due to alternate connection, the addition of ceiling patching, a change to the floor sealer, various painting additions and deducts, reuse of the ground grid and corresponding deduct, a deduct for reuse of conduit within the ATS cabinet to eliminate the need to remove and reset the cabinet, and a deduct for liquidated damages along with some various no cost changes for the temporary pump station structure, manhole restoration schedule and sodding and site restoration.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Water Water Improvements
Water Water Expansion
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action: