Posted: April 27, 2017
Rapid City
Agenda Item Summary

Agenda Item Ref. #: CC050117-02.1 Meade Hawthorne Project

Agenda Item Title:

Approve award of Total Bid for Meade/Hawthorne DBDP Element 48, Project No. 15-2306 / CIP No. 50758 opened on April 25, 2017 to the lowest responsible bidder Underground Construction, LLC, in the amount of $321,800.30.

Origination Group:
City Council
Origination Meeting Date:
05/01/2017
Staff Contact:
Mary Bosworth
Agenda Item Summary:
Construction of drainage channel to replace existing inadequately sized channel and construction of sanitary sewer main to provide services for nonconforming sanitary sewer services.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Storm water 7402
Sewer 833
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Base Bid in the amount of $321,800.30 to Underground Construction, LLC.