Rapid City
Agenda Item Summary

Agenda Item Ref. #: CC030617-04.2 Approve Change Order for Project 17-2377

Agenda Item Title:

Approve Change Order #1 to Lind-Exco, Inc, for an increase of $14,444.58 for removal of additional silt from Landfill Stormwater Pond.

Origination Group:
City Council
Origination Meeting Date:
03/06/2017
Staff Contact:
Karl Merbach
Agenda Item Summary:
The Solid Waste Division has undertaken a silt removal project on the landfill stormwater pond. The original drawings were used to determine the bottom elevation of the pond in combination with a surface survey to calculate the amount of silt. During the work, it was discovered that the bottom was not at the elevations listed in the drawings. This created the need to remove an additional 2,584 cubic yards of silt. As noted, this project has begun, and approval of this change order for the additional work is time-critical so that work may be completed ahead of the need for the pond to be used for stormwater.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
7104 4371

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

  pdf Change Order