Agenda Item Summary

Agenda Item Ref. #: PW021125-01

Agenda Item Title:

PW021125-01: Approve Change Order 1F To RCS Construction For Wildwood Drive Reconstruction Phase 2 For Project No. 2506/CIP No. 51003 For A Decrease Of $390,167.66.

Origination Group:
Public Works Committee
Origination Meeting Date:
02/11/2025
City Council Hearing Date:
02/18/2025
Staff Contact:
LIndsey Martin
Agenda Item Summary:
This is a final change order reconciling final quantities. Total project cost $5,106,044.29.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
CIP Drainage
Enterprise Water
Enterprise Water Reclamation
Is Funding Budgeted?:
Budgeted

Recommendations: