Approve Change Order #1 to Mainline Contracting, Inc. for Sheridan Lake Road Reconstruction –Utility, Wall & Sidewalk Breakout Project, Project No. 2736, CIP No. 51122.1, for an increase of $52,367.35.

Origination Group:
Public Works Committee
Origination Meeting Date:
11/14/2023
City Council Hearing Date:
11/20/2023
Staff Contact:
Roger Hall
Location:
Sheridan Lake Road
Agenda Item Summary:
This change order is to address unforeseen circumstances, upgrades for city infrastructure, and additional work that will aid in the constructability of the upcoming Sheridan Lake Road reconstruction project.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
Is Funding Budgeted?:
Budgeted

Recommendations: