Posted: May 05, 2023
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW050923-02

Agenda Item Title:

Authorize Staff to Advertise for Bid for the 143rd Avenue and Country Road Trunk Sewer Extension, Project No. 22-2694 / CIP 51220. Estimated Cost $7,800,000.

Origination Group:
Public Works Committee
Origination Meeting Date:
05/09/2023
City Council Hearing Date:
05/15/2023
Staff Contact:
Nicole Lecy
Agenda Item Summary:
The project includes the extension of a 24” trunk sewer main from the existing 24” main at the intersection of 143rd Avenue and Seger Drive to the Country Road Lift Station with a total length of approximately 1.5 miles. The need for this project has been identified by the City’s Utility System Master Plan. Peak sewer flows contributing to the Country Road Lift Station have exceeded the lift station capacity and this project will allow for the decommissioning of the lift station. The roads impacted by the sewer construction will be rebuilt as rural pavement sections.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Wastewater Replace/improve
Wastewater Expansion
CIP Streets ARPA
Grant Funding
Is Funding Budgeted?:
Budgeted

Recommendations: