Agenda Item Summary

Agenda Item Ref. #: PW112922-02

Agenda Item Title:

Authorize Lowering The Percentage Of Work That The Contractor Must Perform With Their Own Organization From 50% To 35% For The Reservoir Road Rehabilitation And Manhole Repair Project, Project No. 22-2712 / CIP No. 51356.

Origination Group:
Public Works Committee
Origination Meeting Date:
11/29/2022
City Council Hearing Date:
12/05/2022
Staff Contact:
Nicole Lecy
Agenda Item Summary:
Revise Paragraph 7.40 of Section 7 - General Conditions of the City of Rapid City Standard Specifications to allow the Contractor to perform not less than 35% of the work with their own organization instead of the standard 50% for the Reservoir Road Rehabilitation and Manhole Repair Project. Based on the scope of work for the project, multiple subcontractors are anticipated and no one contractor will likely encompass 50% of the work thus it may be difficult for Contractors to meet the 50% requirement.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Wastewater Replace/Improve
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve