Print this page
Posted: June 10, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW061422-01

Agenda Item Title:

Approve Change Order #4F to Simon Contractors of SD Inc. for 12th Street Reconstruction – West Main to Fulton Street, Project 19-2499 / CIP No. 50927, for an increase of $59,404.87

Origination Group:
Public Works Committee
Origination Meeting Date:
06/14/2022
City Council Hearing Date:
06/20/2022
Staff Contact:
Roger Hall
Location:
12th Street
Agenda Item Summary:
Additional sewer services were encountered during construction which had not been previously known or shown in the plans. After investigation, the City determined to extend sanitary sewer mains up Quincy Street from the existing main in the 12th Street Alley and then south in 12th Street. Sewer services were then connected to this new main from the affected residences.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
Water Replacement
CIP Drainage
Sewer Replacement
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

PW061422 01 Project 2499 CO ( pdf, 2.99 MB )