Print this page
Posted: August 07, 2019
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW081319-08

Agenda Item Title:

Authorize Mayor and Finance Officer to Sign an Agreement between the City of Rapid and Longbranch Civil Engineering, Inc. for Professional Engineering Services for Robbinsdale Phase 6 Design, Project No. 19-2515, CIP No. 51232, in the amount of $517,084.00.

Origination Group:
Public Works Committee
Origination Meeting Date:
08/13/2019
City Council Hearing Date:
08/19/2019
Staff Contact:
Doug Noyes
Location:
Parkview Dr
Agenda Item Summary:
The Long branch Civil Engineering, Inc. will provide design and bid packages for four separate bid projects. 1. Robbinsdale Phase 6A - Parkview Water Main Replacement of the water main in Parkview Dr from Fairmont to Liberty. Frequent and costly maintenance issues have expedited replacement of the watermain. 2. Robbinsdale Phase 6B - Parkview Drive Reconstruction Reconstruction of the street (pavement, sidewalk, curb and gutter) sanitary sewer, and storm sewer in Parkview Dr from Fairmont to Liberty and Elk St from Anaconda to Elm. 3. Robbinsdale Phase 6C - Fairlane Drive Reconstruction Reconstruction of the street (pavement, sidewalk, curb and gutter) sanitary sewer, and storm sewer in Fairlane from Fairmont to Elm, Elm from Utah to Fairmont, and Utah from Elm to west of Willow. 4. Robbinsdale Phase 6D - Fairmont Utility Reconstruction Water and sanitary sewer replacement, a pressure zone change, and minor street reconstruction in Fairmont Blvd from Elm to Grandview Dr.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
604 Wastewater Enterprise 0833 Wastewater Replacement
602 Water Enterprise 0933 Water Replacement
505 CIP 8910 Streets
505 CIP 8911 Drainage
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve