Posted: May 09, 2019
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW051419-02

Agenda Item Title:

Approve Change Order #SF to Western Construction, Inc. for Catron Boulevard Widening Project, Project# 16-2343/CIP 51115 for an increase of $11,200.00.

Origination Group:
Public Works Committee
Origination Meeting Date:
05/14/2019
City Council Hearing Date:
05/20/2019
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order #SF to Western Construction, Inc. for Catron Boulevard Widening Project, Project# 16-2343/CIP 51115 for an increase of $11,200.00. Liquidated damages days were decreased to 81 days from 95.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
505 8901
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

PW051419-02 Change Order 2343