Print this page
Posted: April 26, 2018
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW050118-02

Agenda Item Title:

Approve Change Order 1 to Site Works Specialist, Inc. for Sturgis Road Area Utility Reconstruction and Extension, Project No. 11-2001 / CIP No. 50824, for an increase of $16,827.54.

Origination Group:
Public Works Committee
Origination Meeting Date:
05/01/2018
City Council Hearing Date:
05/07/2018
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order 1 to Site Works Specialist, Inc. for Sturgis Road Area Utility Reconstruction and Extension, Project #11-2001/ CIP 50824 for an increase of $16,827.54.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Water Water Improvements
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

  pdf Change Order