Posted: November 15, 2016
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW111516-02

Agenda Item Title:

Approve Change Order #1 to R.C.S. Construction for Baldwin Reconstruction, Project No. 14-2189 / CIP No. 50822.1-1 for an increase of $23,850.28.

Origination Group:
Public Works Committee
Origination Meeting Date:
11/15/2016
City Council Hearing Date:
11/21/2016
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Change Order #1 to R.C.S. Construction for Baldwin Reconstruction Project #14-2189/CIP 50822.1-1 for an increase of $23,850.28.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Sanitary Sewer Sanitary Sewer Improvements
Water Water Improvements
Drainage Drainage Improvements
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve