Print this page
Posted: March 31, 2016
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW032916-01

Agenda Item Title:

Approve Change Order No. 1 to Mainline Contracting for 9th Street Reconstruction – Fulton to Columbus, Project No. 14-2208 / CIP No. 50435, for an increase of $7,587.96.

Origination Group:
Public Works Committee
Origination Meeting Date:
03/29/2016
City Council Hearing Date:
04/04/2016
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Increase to the contract based on actual qualities installed.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
Water Replace/Improve
CIP Drainage
Sewer Replace/Improve
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve
City Council Recommendation Action:
Approve