Agenda Item Ref. #: CC011723-04.2 12th Street Reconstruction, Fulton to Fairview Street

Agenda Item Title:

Approve award of total bid for 12th Street Reconstruction Fulton Street to Fairview Street, Project No. 21-2642 / CIP No. 51324 opened on January 10, 2023 to the lowest responsible bidder, Underground Construction, in the amount of $1,528,795.65.

Origination Group:
City Council
Origination Meeting Date:
01/17/2023
Staff Contact:
Brandon Quiett, PE
Agenda Item Summary:
Project includes water, sewer, storm sewer, and street reconstruction of 12th Street and associated tie-ins at intersecting streets. This is the final project for the reconstruction of 12th Street and the last of a series of projects to extended storm sewer from Rapid Creek into the West Boulevard area.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
602 933
604 833
505 8910
505 8911
Is Funding Budgeted?:
Budgeted
Funding Source & Fiscal Impact Notes:
Award: Total Bid in the amount of $1,528,795.65 to Underground Construction.

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $1,528,795.65 to Underground Construction.